Conventional workflow, and OpenBrIM

The same bid period, two ways of working.

Time to a code-checked answer

Conventional
modelanalyzechecktake-off
With OpenBrIM
one loop

Conventional work redoes the model, analysis, checks and take-off for each what-if. In OpenBrIM one model runs all four.

Options code-checked in full per ATC round

Conventional
3 to 5
With OpenBrIM
tens, from billions searched

The few the team reviews are picked from far more than a conventional workflow can model.

Bar lengths are relative.

Price decides most awards

The owner turns price and technical points into one ranking, so the search is for the best price and schedule the formula will reward.

81% of 113 best-value design-build highway projects went to the lowest bidder Source: Best-Value in the Procurement of Highway Projects, IntechOpen

How it works

The AI decides what to try next, within the engineer of record's design criteria and steered by the team's feedback. Deterministic OpenBrIM software calculates the engineering, the quantities and the score.

Pursuit team designers · contractors · OpenBrIM feedback Search steered by the team Calculated deterministic: same inputs, same numbers AI agent chooses what to try next within the design criteria Generate parametric model billions of options Analyze 3D finite elements construction stages Check AASHTO LRFD RFP limits Quantify pay items activities, durations Score owner's formula public cost data parameters to try checked results, score Every check traces to its model, load case and AASHTO article Pursuit team designers · contractors · OpenBrIM feedback AI agent chooses what to try next within the design criteria Calculated: same inputs, same numbers Generate parametric model billions of options Analyze 3D finite elements construction stages Check AASHTO LRFD RFP limits Quantify pay items activities, durations Score owner's formula public cost data parameters checked results, score Every check traces to its model, load case and AASHTO article

What the score uses

Public cost data

Cost in the search comes from public data, applied to each option's quantities.

Team inputs, weighted

What the designers and the contractor add, such as production rates, crane sizes or fabrication limits, counts with the weight the team gives it.

Unit costs stay with the contractor

Quantities go out; one total per alternative comes back and counts like any other team input.

One alternative, start to finish

Every alternative that reaches the team went through this loop.

ParametersModelAnalysisChecksObjectivesScore
previous: 3 spans, 72 in girders M 0.710.860.970.880.930.990.840.69clearance16.5 ft ✓ At pier 3, negative flexure: D/C 0.99Strength I · AASHTO LRFD 6.10.8.1.1 52 t24 t38 t25 t37 t24 t51 theaviest crane pick 52 t Spans 3 → 4Girder depth 72 → 84 inErection: craneGirders, deck, piers, footings, piles3D finite elements, 6 construction stagesAASHTO LRFD and RFP limits: pass7 field pieces per girder lineOwner’s formula: rank 3 of 40Next: spans 4 → 5
1,320 tsteel
3,260 C.Y.concrete
35field pieces
52 theaviest pick
26 moduration
Alternative 1,284,903
billions→thousands→hundreds→tens→5 to 20
Example values
01 · Parameters

Change the parameters

The agent picks spans, girder type and depth, piers, foundations and the erection method, within the engineer of record’s design criteria and the contractor’s construction limits.

02 · Model

OpenBrIM builds the model

Girders, deck, piers, footings and piles come from the bridge library, with their construction stages.

03 · Analysis

Run finite element analysis

A 3D model, stage by stage, the way it will be built.

04 · Checks

Check the specification

AASHTO LRFD, and the RFP’s own limits: clearances, spans, staging. Each ratio traces to its limit state, load combination and article.

05 · Objectives

Measure what it takes to build

Quantities, fabrication pieces, crane picks and schedule are the objective functions. They come out of the same model.

06 · Score

Score it, then try the next

The owner’s formula turns them into one number and a rank. Then the agent tries the next option. Of billions of options, tens are code-checked in full and 5 to 20 reach the team.

Ranked by the owner's award formula

A saving and a lost technical point become one number.

price as bid −$15.0M +$6.25M −$8.75M Cost saving from the alternative Half a point lost × $12.5M per point Net effect on the ranking

Price ÷ technical score, $1.0B bid scored 80: one point is worth about $12.5M. A $15M saving that costs half a point still comes out $8.75M ahead in the owner's ranking. The team sets the expected point change; the formula turns it into dollars.

Who does what

The OpenBrIM team joins yours for the pursuit. Each party keeps the decisions it is responsible for.

OpenBrIM team and AI agent

Joins the pursuit and every review. Runs the search, analysis, checks and quantities in the design firm's workspace, and prepares ATC backup.

Responsible for the software and for running the search
ranked alternatives criteria, changes
Design firm, engineer of record

Owns the models and the design criteria. Reviews each round, adopts and seals.

Responsible for the engineering
Adopted and sealed
quantities one total each
Contractor

Chooses methods, feeds back each round, prices in-house and submits the price.

Responsible for the price, means and methods
Unit costs stay here

Steps

No project data is shared before the NDA.

Before we start

about a week · no charge until you accept the quote
  1. Contact and conflict check
  2. NDA and project data
  3. Quote, then licence if needed

Bid period

Quoted per pursuit
  1. Base conceptfirst 2 weeks
  2. Alternativeseach ATC meeting
  3. ATCslast ATC date
  4. Proposaldue date

After award

OpenBrIM licence
  1. Final design

Each review round, in the team's OpenBrIM workspace

  • Pay-item quantities, live from the model
  • Field pieces and crane picks
  • Activities and durations
  • Check summary with AASHTO articles
  • ATC backup for the engineer of record

Terms

The same for every pursuit.

One team per procurement

No competing team, and not the owner. We don't tell other teams who asked. The OpenBrIM licence stays open to every client.

The engineer of record decides

The design firm, as engineer of record, owns the models and the design criteria, and adopts and seals the design. Criteria change only with its approval.

Your data stays yours

NDA first. No unit costs asked. Data stays in the design firm's workspace, and the contractor's inputs are seen only by the pursuit team. Our access ends with the pursuit.

Priced per pursuit

Suggested from the bridge construction budget, and it varies per project. See Pricing below.

Pricing

Two parts. The licence applies only when the team's design firm is not yet an OpenBrIM client.

OpenBrIM licence
from$3,000per month

For a design firm that does not have OpenBrIM yet. The pursuit runs in its workspace, and the models stay with it for final design.

Pursuit AI
starting budget$50,000per pursuit

We suggest the budget from the bridge construction budget you send us (see below). It varies per project.

Discuss a pursuit

Email us the owner and project, the proposal due date and the bridge construction budget. We reply to say whether the procurement is still open (no other team has it), with a suggested budget; it varies per project.

Email info@openbrim.org

No confidential material in the email. Project data goes into the design firm's OpenBrIM workspace after the NDA.